Tue, 24 Dec 2024

OMOTOSHO POWER PLANT

PRESIDENT GOODLUCK COMMISSIONS OMOTOSHO POWER PLANTS PHAZE II
 
By:
Sat, 19 Oct 2013   ||   Nigeria,
 

President GoodLuck Jonathan on Saturday, commissioned the 500 megawatts Omotosho Power Plant Phase 2 with four gas turbines in Ondo State.

This is coming exactly 16 days after the commissioning of the 434MW Geregu II plant in Kogi State and also the second of the 10 Nigerian Independent Power Project (NIPP) under the management of the Niger Delta Power Holding Company (NDPHC) Ltd to be inaugurated.

It is moreover exciting to note that the Omotosho Power Project which is commissioned today was initiated in 2004 and has been abandoned between 2007 and 2009 due to funding problems.

Congratulating the President for his commitment and land marks in revitalizing the power sector, the Honorable Minister of power, Professor Chinedu Nebo remarked that the power sector has enjoined the position of No. 1 priority in this administration.

Speaking at the event, President Goodluck Jonathan noted that the new development was aimed at boosting the country’s capacity in generating 500MW of energy.

President also utilized the occasion to assure PHCN workers that are yet to get their severance package that the government is working towards that, urging them that there is no need for industrial action.

 