The Ministry of Power, Works and Housing has threatened to end the contract for the dualisation of the Abaji-Koton-Karfe road due to “negligence” by the contractor for five months.
The Director of Highways Constructions and Rehabilitation of the ministry, Mr Dayyabu Mamman issued the threat on Wednesday during an inspection by the Minister of State II for Power, Works and Housing, Suleiman Zarma.
The minister in the company of some ministry’s officials was on an inspection of the Federal highways projects in Kogi state, including housing projects.
The project which is being handled by Bulletine Construction Company Ltd at the cost of N15. 1 billion is part of the dualization of the Abuja-Lokoja Road; section III (Abaji-Koton-Karfe) C/No.5884.
The 49.40 km road construction which began on Oct. 12, 2006 with initial completion date of April 11, 2009 but extended completion date of March 12, 2014 has 159.72 as per cent time lapse.
Mamman, also the North-Central Zone Director noted that the contractor who has spent 12 years on the project with only 54.48 per cent completion and has applied for extension of contract period.
He identified another challenge facing the project as the “Rutting on the carriage way’’ report which the department of Materials and Geotechnic has conducted pavement evaluation test to certify the reason for the failure but has not been submitted. The Engineer also ascribed delay in the project to high rate of accidents on the road due to untidiness of the site.
Mamman recalled that the contractor has been issued warning letters for poor performance and series of meetings have equally been held with the contractor to encourage increase performance but it yielded no result.
Meanwhile, the company’s site agent, Mr Peter Omenye confirmed that the contract was abandoned because of labor related issues concerning workers’ salaries and entitlement
According to him, the workers have refused to work until they are paid all their entitlements.
Reacting to this, the minister noted that there was every reason to terminate the contract because the contractor has not been on site for five months because of domestic issues.
However, Zarma who is also a Surveyor noted that in terms of contractor’s conditions, the ministry would go into the documents to look at the contractor’s conditions before making categorical statement.
Zarma also inspected the dualisation of Abuja-Lokoja road, section IV (Koton-Karfe-Lokoja) Obajana junction, C/No. 5885 being handled by Gitto Construction Company with 61 per cent completion.
The minister had earlier inspected the dualisation project of Abuja-Abaji-Lokoja road (section 1), contract No. 5862 including spur to Airport junction.
He lauded the road work progress, emphasising that there was fulfilment of President Muhammadu Buhari’s commitment to fix infrastructure deficit in the country.
He said road project were always costly due to outsourcing of raw materials such as granite and cement including conducting soil test before actual project execution commenced.
CEOAfrica gathered that the percentage completion of the project being handle by Dantata and Sawoe construction Ltd. as at April 2018 is 90 per cent while the financial expenditure as at January 2017 is 88 per cent.
The major works completed include the construction of new road (11.4km) along Airport road Spur, rehabilitation of existing road (10.04KM), and construction of interchange at Giri and Gwagwalada among others.